Karoon plans new rig intervention at Baúna after SPS-92 electrical fault

By Westhon MediaSeptember 29, 2026 at 09:24 AM2 min read
Share

Karoon Energy is preparing another rig-based intervention on the SPS-92 well at the Baúna Project, offshore Brazil, after an electrical fault affected the recently installed system supplying its downhole electric submersible pump.
​
The fault was detected on September 21. Karoon carried out a controlled shutdown the following day and later confirmed a fault in one of the three electrical phases of the newly installed power cable.
​
The ESP has since been restarted on two phases and is operating under a conservative operating envelope.
​
According to Karoon, SPS-92 produced 8,250 bopd during its latest well test on September 16. Following the electrical fault, production is currently around 4,700 bopd, representing approximately 3,500 bopd of deferred output.
​
The timing is significant: the new ESP and cable system had been operating for just 87 days.
​
SPS-92 returned to production in late June following a previous rig-based intervention to replace its ESP. At the time, the well was producing approximately 8,600 bopd.
​
Karoon now expects another rig intervention will be required to restore full operability. The company has an existing option over a suitable drilling rig and has started planning the campaign, including permitting, equipment and services.
​
Karoon also confirmed that the rig used for the previous SPS-92 intervention will not be used for the new campaign. The replacement unit has not yet been identified.
​
The company has started discussions with Ibama to determine whether the new intervention could be treated as a second phase under the previous environmental permits. Timing remains dependent on regulatory approvals, rig availability and supporting services.
​
As a result of the reduced SPS-92 output, Karoon has lowered its 2026 Baúna production guidance from 6.0–6.7 million barrels to 5.4–5.7 million barrels. The company currently does not expect the deferred production to affect Baúna reserves.

This article was produced by Westhon Media for One Energy News.