Beyond new FPSOs: the offshore workload behind Petrobras’ investment plan
Also available in Portuguese
Além das novas FPSOs: a carga de trabalho offshore por trás do plano de investimentos da PetrobrasRead in Portuguese →Automatically generated translation; may contain errors.
Petrobras’ 2027–2031 Business Plan outlines an offshore workload spanning well construction, subsea connections, maintenance and decommissioning. For vessel owners and contractors, the distribution of that work provides a useful perspective on the US$122 billion investment forecast.
Approved on 23 November 2026, the plan includes US$113 billion in the implementation portfolio and US$9 billion in projects under evaluation. Nine new production systems are scheduled within the five-year period, eight already contracted and one undergoing contracting.
The detailed presentation provides a more concrete measure of planned activity: approximately 250 wells to be constructed, 280 to be connected and 200 abandonment interventions involving subsea-completed wells between 2027 and 2031. These figures cover distinct activities and should not be added together as a total well count.
Existing production systems are central to the strategy. Petrobras has allocated approximately US$14 billion to complementary projects, including drilling, completion and connection of around 100 offshore producer and injector wells. These projects are expected to account for approximately 10% of average total production over the period.
The programme includes developments at Roncador, Barracuda/Caratinga, Marlim Sul and Jubarte in the Campos Basin, alongside Tupi, Itapu and Búzios in the Santos Basin. This points to work around producing fields as well as new production units.
The spending mix also matters. Petrobras estimates that approximately 60% of expenditure on subsea activity vessels will support connections, equipment installation, mooring and rig support. Inspection and maintenance account for around 30%, with decommissioning representing the remaining 10%. These percentages describe expenditure, not vessel numbers or utilisation.
At the other end of the asset lifecycle, the plan identifies 27 platforms for removal during 2027–2031 and approximately 1,900 kilometres of flexible lines to be recovered. These activities bring their own technical requirements alongside the work needed to sustain and expand production.
For the offshore market, this suggests that vessel capability and scheduling will be as important as the headline investment figure. Installation, inspection, maintenance and removal require different equipment and execution strategies, even where vessels can move between scopes.
Petrobras says its planning increasingly considers the interdependence of rigs and PLSVs, seeking flexibility in resource allocation. The plan provides a basis for assessing future demand; individual tenders, project schedules and contract awards will determine how that demand reaches the market.